środa, 15 czerwca 2011

questions and answers for tests PMP

and now the questions and answers for tests

1. Which of the following it the logical flow of any project?
A. Planning, Initiating, Executing, Controlling, Closing
B. Initiating, Planning, Controlling, Executing, Closing
C. Planning, Initiating, Executing, Controlling, Closing
D. Initiating, Planning, Executing, Controlling, Closing
2. In which phase of a project would you estimate activity duration and resources?
A. Initiating
B. Executing
C. Planning
D. Controlling
Answer Key
1. D


2. Parento diagrams work on the ___ rule.
A. 50/50
B. 60/40
C. 80/20
D. 90/10
Answer Key
2. C.
Have a nice learning!!!