środa, 14 września 2011

PMP Test Questions

What has an expected duration, and expected cost, and expected resource requirements and must be performed to produce deliverables?

A. Schedule
B. Task
C. Activity
D. Milestone

2. You plan to start your project with a kick-off meeting where you will present your plan and introduce the team members with their roles in the project. The meeting agenda has been published early enough to allow everyone to have enough time to plan for the participation at the meeting. To your surprise the day before the meeting you receive several phone calls from the assigned team members explaining that they cannot participate in the meeting due to other commitments. What do you do in this situation?

A. You cancel the meeting because the kick-off meeting is not that important.
B. You cancel the meeting because forcing the meeting on the team members you would not get their attention during the meeting.
C. You reschedule the meeting when every team member is available.
D. You insist on the meeting as scheduled and every team member to participate.

3. . For your project you decided to use a structured approach to optimize project value. This technique analyzes qualitative and quantitative costs, as well as the benefits of component parts of the proposed system. Which technique did you decide to use?

A. Value engineering
B. System engineering
C. Value analysis
D. Function analysis

4. During stakeholder identification you group the stakeholders based on their level of authority and their level of concern regarding the project outcomes. Which classification model are you using?

A. Power/influence grid
B. Influence/impact grid
C. Power/interest grid
D. Interest/influence grid

5. The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is called?
A. Control Budget
B. Estimate Budget
C. Create Cost Baseline
D. Determine Budget

6. You are the project manager of a FFP contract. The contract value is $560,000 and your company expects a 10% profit. You have completed the work and the customer has signed the completion document. While you are preparing your final performance report you figure out that your cost has reached $558,000. Which amount do you bill your customer?

A. $558,000
B. $560,000
C. $613,800
D. $616,000

Brak komentarzy:

Prześlij komentarz